Following on from the previous couple of posts concentrating on Court Street, here is another of Merthyr’s Bridges.
Court Street Railway Bridge
In 1851 the Vale of Neath Railway was constructed to carry goods from the Merthyr Ironworks to Neath, and then onto Swansea for export by sea. The line originally stopped at Aberdare, but with the construction of the Aberdare/Merthyr Tunnel the line finally reached Merthyr in 1853.
The Court Street Railway Bridge was built in 1852 to carry the new line to Merthyr Station, over the main parish road to Twynyrodyn.
The original bridge was built on a slight skew and had three spans – the main central span for road traffic of 24 ft 9in, and two smaller side spans for pedestrians of 8ft each. The bridge was built with dressed stone abutments and piers, with a wrought iron ‘trough’ across them to carry the railway.
From the time of its construction, the bridge was prone to problems with large volumes of water coming off the bridge on to the traffic below. The Vale of Neath Railway, and later the Great Western Railway (when they took over the Vale of Neath line) continually tried to rectify the problem, but without success.
In 1938, the GWR requested permission to reconstruct the bridge, but this was denied. In 1946 however, permission was granted for the bridge to be modified, with a single trestle being built in place of the side piers. As a result of this modification, only one pedestrian footpath could now be used due to the base of the trestle being built on the other side.
In 1963, British Rail and Merthyr Borough Council agreed that a new bridge should finally be built to accommodate the increase, and type of traffic using the roadway. Work began in 1965, with the removal of the old urinal at the bridge, and the road was lowered to provide more headroom for traffic. The new single-span bridge, built of masonry abutments and stressed concrete beams was opened in 1967, and the bridge is still in use today.